    Journal of the Southern African Institute of Mining and Metallurgy

    versión On-line ISSN 2411-9717versión impresa ISSN 2225-6253

    J. S. Afr. Inst. Min. Metall. vol.108 no.4 Johannesburg abr. 2008

     

    JOURNAL PAPER

     

    Double-header trains at Great Noligwa mine

     

     

    L. van Dyk

    University of Johannesburg

     

     


    SYNOPSIS

    The project was aimed at evaluating the double-header trains implemented at Great Noligwa mine, looking at the changes from the old conventional trains to the new trains, and identifying possible improvements to obtain an even better and more productive tramming system. The methods used to evaluate the double-header trains at the mine included personal observations, time studies, personal interviews, technical research, safety analysis, cost analysis, production analysis, breakdown analysis, break test analysis, comparisons and working closely with engineering department and manufacturers.
    Issues that were evaluated are the improvements in safety, cost reductions, tramming congestion reductions, better efficiencies, labour optimization, enhanced driver safety and maintenance. Shortcomings of the double-header trains were identified and recommendations made to improve on the shortcomings.
    Findings of the evaluation study indicated the following:
    Drastic improvement on safety
    Extreme cost reductions
    Reduction in tramming congestions and bottlenecks
    Better tramming efficiencies
    Optimized labour placement
    Enhanced driver safety
    More effective maintenance.
    Although there is room for improvements, the double-header trains were implemented with great success at Great Noligwa mine. It is currently the preferred tramming methodology at Great Noligwa mine, and is also implemented at other Anglo Gold Ashanti-South Africa shafts. This tramming system has huge potential for growth, not only in Anglo Gold Ashanti, but in all other older mines that experience major tramming problems.


     

     

    “Full text available only in PDF format”