Open-access Exploiting deterministic maintenance opportunity windows created by conservative engineering design rules that result in free time locked into large high-speed coupled production lines with finite buffers

Abstract

Conservative engineering design rules for large serial coupled production processes result in machines having locked-in free time (also called 'critical downtime' or 'maintenance opportunity windows'), which cause idle time if not used. Operators are not able to assess a large production process holistically, and so may not be aware that they form the current bottleneck - or that they have free time available due to interruptions elsewhere. A real-time method is developed to accurately calculate and display free time in location and magnitude, and efficiency improvements are demonstrated in large-scale production runs.


location_on
The Southern African Institute for Industrial Engineering The Southern African Institute for Industrial Engineering, P.O. Box 96002, Waterkloof, Pretoria, Gauteng, ZA, 0145, Tel: +27 12 420 6478 - E-mail: admin@saiie.co.za
rss_feed Stay informed of issues for this journal through your RSS reader
Go to top