Open-access Improving accuracy of wind resource assessment through feedback loops of operational performance data: A case study in South Africa

Abstract

This study addresses two key objectives using operational performance data from most of the Round 1 wind farms connected to the grid in South Africa: benchmarking of wind farm performance and validation of the pre-construction energy yield assessments. These wind farms were found to perform in line with internationally reported levels of wind farm availability, with a mean energy-based availability of 97.8% during the first two years of operation. The pre-construction yield assessments used for financing in 2012 were found to over-predict project yield (P50) by 4.9%. This was consistent with other validation studies for Europe and North America. It was also noted that all projects exceed the pre-construction P90 estimate. The reasons for this discrepancy were identified, with the largest cause of error being wind flow and wake-modelling errors. Following a reassessment using up to date methodologies from 2018, the mean bias in pre-construction predictions was 1.4%. Highlights: • Operational wind farms in South Africa compared to preconstruction predictions. • Energy yield assessments in 2012 averaged 4.9% over-prediction. • Largest causes of bias wake modelling and long-term windspeed adjustment. • Modern techniques significantly improve prediction accuracy.

operational yield; wind farms; validation; benchmarking; renewable energy


location_on
The Department of Chemical Engineering of the University of Cape Town Department of Chemical Engineering, University of Cape Town, Private Bag X3, Rondebosch, Cape Town, Western Cape Province, ZA, 7701, Tel: +27 21 650 3892 - E-mail: journalofenergysouthernafrica@gmail.com
rss_feed Acompanhe os números deste periódico no seu leitor de RSS
Ir para o topo