Open-access Measurement and verification of a lighting load reduction project through energy efficiency

This paper will describe the methodology and procedures that were followed to measure and verify the impact on the electricity use of a lighting load reduction project implemented at a gold mine. The lighting retrofit was concentrated on the 100 level and 100 incline of the gold mine. Since the lights were underground, it was operational for 24 hours each day. The proposed project activity aimed to reduce the electric demand of the lighting system by replacing the current types of lighting fixtures with more energy efficient units. The possibility existed to reduce the lighting load by 157 kW. These impacts needed to be assessed in order to verify the DSM impacts and savings for the client, the ESCO and Eskom. Pre-implementation metering was done in order to determine the operational and installed capacity of the original lighting system. Together with the number of lights affected by this project activity and the 24-hour operational profile, this data defined the baseline electricity use of the project. The same metering techniques and layout have been used after implementation to determine the new installed and operational capacity of the new lighting system. This project achieved 99.36% of its contracted target of 157kW.

lighting efficiency retrofit; M& V of lighting retrofits; efficient lighting upgrade; M& V of EE-DSM projects


Measurement and verification of a lighting load reduction project through energy efficiency

Idah Masopoga; Christo van der Merwe; LJ Grobler

School of Mechanical Engineering, North West University, Potchefstroom

ABSTRACT

This paper will describe the methodology and procedures that were followed to measure and verify the impact on the electricity use of a lighting load reduction project implemented at a gold mine. The lighting retrofit was concentrated on the 100 level and 100 incline of the gold mine. Since the lights were underground, it was operational for 24 hours each day. The proposed project activity aimed to reduce the electric demand of the lighting system by replacing the current types of lighting fixtures with more energy efficient units.
The possibility existed to reduce the lighting load by 157 kW. These impacts needed to be assessed in order to verify the DSM impacts and savings for the client, the ESCO and Eskom. Pre-implementation metering was done in order to determine the operational and installed capacity of the original lighting system. Together with the number of lights affected by this project activity and the 24-hour operational profile, this data defined the baseline electricity use of the project. The same metering techniques and layout have been used after implementation to determine the new installed and operational capacity of the new lighting system. This project achieved 99.36% of its contracted target of 157kW.

Keywords: lighting efficiency retrofit, M&V of lighting retrofits, efficient lighting upgrade, M&V of EE-DSM projects

Full text available only in PDF format.

References

  • Grobler L.J. and den Heijer W., - The Measurement and Verification Guideline: 2006.
  • International performance measurement & verification protocol (IPMV), 2002.
  • Masopoga I.M. and van der Merwe C.A., Measurement and verification reports for underground mine lighting retrofit: 2007.

Received 29 October 2007
Revised 27 July 2009

Publication Dates

  • Publication in this collection
    15 May 2015
  • Date of issue

History

  • Received
    29 Oct 2007
  • Accepted
    27 July 2009
location_on
The Department of Chemical Engineering of the University of Cape Town Department of Chemical Engineering, University of Cape Town, Private Bag X3, Rondebosch, Cape Town, Western Cape Province, ZA, 7701, Tel: +27 21 650 3892 - E-mail: journalofenergysouthernafrica@gmail.com
rss_feed Acompañe los números de esta revista en su lector de RSS
Ir para arriba