SciELO - Scientific Electronic Library Online

 
vol.121 issue9A novel economic-filter for evaluating sub-Saharan diamondiferous kimberlites author indexsubject indexarticles search
Home Pagealphabetic serial listing  

Services on Demand

Article

Indicators

Related links

  • On index processCited by Google
  • On index processSimilars in Google

Share


Journal of the Southern African Institute of Mining and Metallurgy

On-line version ISSN 2411-9717
Print version ISSN 2225-6253

J. S. Afr. Inst. Min. Metall. vol.121 n.9 Johannesburg Sep. 2021

http://dx.doi.org/10.17159/2411-9717/1564/2021 

PAPERS OF GENERAL INTEREST

 

Determination of the optimal transition point between a truck and shovel system and a semi-mobile in-pit crushing and conveying system

 

 

M. ShamsiI; M. NehringII

ISchool of Mining Engineering, Faculty of Engineering, University of Tehran. https://orcid.org/0000-0001-7555-8568
IISchool of Mechanical and Mining Engineering, Faculty of Engineering, University of Queensland. https://orcid.org/0000-0002-0404-5332

Correspondence

 

 


SYNOPSIS

One of the most challenging aspects in semi-mobile in-pit crushing and conveying (SMIPCC) system design is determining the optimum depth at which to change from a purely truck-based haulage system to a conveyor-based haulage system. We used scenario analysis to determine the optimum transition depth between a truck and shovel (TS) system and a SMIPCC system. Traditional pit-limit algorithms were used to generate the final pit limit on a copper deposit, which was then divided into four pushbacks. The final operating pushbacks (phases) were designed for both TS and SMIPCC. The end depths for each phase are viewed as candidate transition points to switch from the TS to SMIPCC haulage system. Economic calculations were applied for five different scenarios, including adopting SMIPCC from the outset (pure SMIPCC), after the first, second, and third phases, and finally not using the SMIPCC system (pure TS) at all. The analysis indicates that the second scenario, at a depth of 335 m, results in the lowest cumulative discounted cost (CDC). In this case, the CDC is 17.6% lower than that for the pure TS scenario and 10.7% lower than for the pure SMIPCC system scenario.

Keywords: Open-pit mining, mining transportation systems, in-pit crushing and conveying, truck and shovel, transition point.


 

 

Introduction

Mining is considered a cost-intensive industry that will yield a profit when the revenue from selling the valuable product exceeds the cost of producing it across the mine life. For maximum profit, designers are looking to increase precision and the ability to optimize production processes throughout the life of mine (Samavati et al., 2018). One way to enhance profits from mining is to identify expensive production processes and provide operational solutions to reduce the cost of these processes.

Transportation costs have always been a significant part of operating costs in large open-pit mines. This is illustrated in Figure 1, which shows a typical operating cost distribution for a large, deep open-pit mine using the conventional truck and shovel (TS) system. Transportation costs are very variable, depending on pit configuration and geographical location. However, the haulage component is often about 45% of operating costs on a life of mine basis (Tutton and Streck, 2009). As the pit depth increases, the greater the distance and cycle time for trucks hauling material out of the pit. As a result, more trucks are required to transport a specified volume of material. Fluctuations in fuel, tyre, and spare parts prices, and greenhouse gas emissions due to the truck and shovel system, may increase operating costs and cause environmental impacts.

 

 

Due to the depletion of many high-grade and near-surface mineral sources, mining operations have expanded to exploit mostly low-grade and deeper deposits (Osanloo, 2012). Thus, it is necessary to use methods that entail lower extraction costs in addition to greater environmental compatibility so that low-grade and deep mineral resources can be extracted viably.

The concept of using a conveyor belt to transport material from the pit was first mooted at an open pit mine in Germany in 1956, due to the wet and soft ground conditions which made it difficult to use trucks (Koehler, 2003; Utley, 2011). Due to the limited range of materials sizes that could be transported by conveyors (Terezopoulos, 1988), a mobile in-pit crusher system was used for crushing the extracted material. The in-pit crushing and conveying (IPCC) system is a combination of these two types of equipment (conveyor and crusher). Although this system was first used because of poor road conditions, today, advances in the design and construction of conveyors receive more attention. IPCC systems have lower operating costs than TS systems because of their continuous operating regime, reduced labour requirements, and lower energy consumption. However, they require a higher capital cost and are less flexible (Nehring et al., 2018).

In conventional TS mining the extracted materials are loaded into trucks after blasting. Waste materials are sent to a waste dump while ore is sent for primary crushing before being stored on a run-of-mine (ROM) pad prior to feeding into the processing plant. In this method, the crusher is located outside the final pit limit. Due to the short transportation distance in the initial years of mine life, the haulage cycle time is short. However, as the mine life matures and the depth of the mine increases, the distance that material needs to be transported increases. This causes the truck cycle time to lengthen. As shown in Figure 2, the incremental increase in haulage distance reduces the hourly throughput of trucks. This generally results in the need for more trucks, and in turn a significant capital reinvestment. It also increases operating costs. Accordingly, reducing the truck haulage distance may be a good method for decreasing haulage costs (on a tons per hour basis).

 

 

In the IPCC haulage system, extracted material is transported from within the pit by conveyor belts. To do so, materials are initially crushed by an in-pit crusher to a size range that allows efficient transportation to their destination. If the extracted material feeds into conveyors after passing through the crusher, the haulage system is termed a fully-mobile in-pit crushing and conveying (FMIPCC) system. Similarly, if the conveyor belt is fed by trucks, the haulage system is a semi-mobile in-pit crushing and conveying (SMIPCC) system (Frizzell and Martin, 1992). In the SMIPCC system, the transfer of waste or ore from the upper and lower benches to the in-pit crusher is carried out by trucks. This system combines a continuous (conveyor belt) and discontinuous (truck) system and has the advantages of both systems (Paricheh, Osanloo, and Rahmanpour, 2017). In the case of a breakdown in the system (trucks or conveyors), the transportation process may often continue, albeit at a reduced capacity. The SMIPCC system is therefore viewed as a lower risk system and is often thus preferred over FMIPCC, which is a purely continuous system.

Because the transportation route is shorter, a smaller fleet of trucks is required; however, the number of loading machines is the same as for the TS system. To avoid increasing the haulage distance, the crusher(s) location may be changed at regular intervals (Rahmanpour et al., 2014). Using this method can save costs and improve the economics of the operation (Kochanowsky, 1961; Terezopoulos, 1988; Zimmermann and Kruse, 2006; Szalanski, 2010; Dean et al., 2015; Nehring et al., 2018; Paricheh and Osanloo, 2019a; Nunes et al., 2019; Hay et al., 2020). Reduced fuel requirements, energy consumption, and pollutant gas emissions are further benefits of this system (Norgate and Haque, 2013; Purhamadani, Bagherpour, and Tudeshki, 2021).

Numerous researchers have investigated use of an in-pit crusher (Hays, 1983; Huss, 1983), conveyors (Kesimal, 1997; Paricheh and Osanloo, 2019b), and high-angle conveyor (dos Santos, 1984; Mitchell and Albertson, 1985; dos Santos and Stanisic, 1986; dos Santos, 2016; Liu and Pourrahimian, 2021). Others have addressed the problem of optimally locating the crusher (Tudeshki et al., 2004; Konak, Onur, and Karakus, 2007; Roumpos et al., 2014; Paricheh, Osanloo, and Rahmanpour, 2017, 2018; Abbaspour et al., 2019; Paricheh and Osanloo, 2019a, 2019c), and economic advantages and disadvantages. Nevertheless, insufficient research has been done concerning the optimal transition point (time or depth) between a TS system and SMIPCC.

In open-pit mining operations in most developing countries, the material transportation cycle is mainly discontinuous and carried out using the conventional TS system. Due to the superiority of IPCC, if one wants to use this system, the first major question is when or at what depth to shift from the TS to the IPCC system. In this paper we present an innovative approach whereby the end of each pushback/phase is considered as a potential point in the operation to switch the haulage system. Considering five potential transition point scenarios, economic calculations (determining operating and capital costs) are performed for both systems.

 

Subject modelling

Six main steps have been defined and carried out in this study to achieve accurate and consistent comparisons. Figure 3 shows a flow chart of the various aspects of the process used to generate and evaluate the use of IPCC as part of the mine planning process.

 

 

> Step 1: Geological and exploratory review to determine and assess the deposit location and the topography of the area, volume, tonnage, grade, density, and grade-tonnage relationship.

> Step 2: With these new estimations, the possibility of open pit mining is investigated. If the conditions for open pit mining are favourable, the final pit limits and extraction scheduling are then determined. In the case of unfavourable conditions for open pit mining, underground mining methods should be evaluated.

> Step 3: After defining the final pit limit and extraction sequence, operating costs are calculated. According to operational expenses, the final pit limit and schedule may change to achieve the most optimal plan.

> Step 4: At this stage, the utilization of the IPCC system is subjected to a detailed feasibility study. Influencing factors in decision-making include production rate, mine life, topography, weather conditions, environmental laws, access to fuel and energy resources, availability of required machinery, strength and hardness of the rock, etc. Based on these factors, if the implementation of IPCC is not feasible for any reason, the decision part of the flow chart will end. Otherwise, different scenarios are determined to transition the haulage system to IPCC as the depth increases.

> Step 5: At this stage, research is carried out on the equipment for each haulage system (conveyor belt type, width, slope, belt count, and cost of the conveyor belt system, crusher cost, cost of trucks, and truck count). Furthermore, each pushback and final pit limit are redesigned according to conveyor exit restrictions and crusher location.

> Step 6: According to the cost parameters, the CDC of each scenario is calculated. The lowest CDC option should be selected as appropriate to change the method.

Assumptions

A number of assumptions were made in this research as follows:

1. Crushing costs are the same for both in-pit (in IPCC system) and out-of-pit crushers (in the TS system).

2. The same system (TS or SMIPCC) is used for both waste and ore.

3. There is no mixing of ore and waste materials as a result of using the SMIPCC system. In this case, there are separate crusher and conveyor systems for waste and for ore handling.

4. There is only one crusher for ore and one crusher for waste in the SMIPCC system. In the TS system, there is only one fixed ore crusher outside of the final pit limit, while waste material does not need crushing and is delivered to the waste dump directly by truck.

5. Uncertainty related to all parameters such as operating costs (electricity, fuel, crusher movement, etc.) and capital costs (conveyor, crusher, truck, and spreader) has not been considered.

6. The same mathematical final pit limit (not the operating final pit limit) in both TS and SMIPCC systems is assumed. In this case, there is no significant difference between the final pit limits of the SMIPCC and TS systems.

7. The tonnage-grade distribution of the deposit is the same across both systems. Therefore, when considering a constant ore price, the income per ton of ore is the same in both systems. As such, the economic investigation is carried out based on cumulative discounted operating and capital costs.

 

Case study

As a case study, a conceptual cylinder-shaped copper deposit has been used. The average radius and depth of the orebody are 345 m and 670 m respectively, with 20 m of overburden. A block model of the orebody was initially constructed, and nested pits were generated based on different product prices. Technical and economic information that forms the basis of this investigation is provided in Table I. Figure 4 describes the amount of ore, waste, and stripping ratio located within the final pit limit for different copper prices. As the copper price increases, the amounts of ore and waste inside the final pit limit increase. However, the stripping ratio may increase or decrease, depending on (1) increasing the rate of new ore due to conversion of waste to ore as the price increases and cut-off grade decreases; (2) increases in new waste when the final pit is extended and more overburden is required to be removed.

 

 

 

 

A minimum working bench width of 80 m is applied, which in this case generates four pushbacks to fully exploit the pit limit. Figures 5 shows a schematic view of the pushbacks and final pit limit, which is determined based on maximizing profit. Figure 6 shows the ore, waste, and stripping ratio associated with each pushback and final pit limit.

 

 

 

 

After determining the pushbacks, the mine production capacity of 20 Mt per year was derived using Taylor's equation. The final depth of each pushback is considered a potential transition point of the haulage system from TS to IPCC. The centre of gravity of ore and waste for each pushback was used to best locate the in-pit crusher.

Five scenarios are considered in total, as follows:

1. SMIPCC used from the outset (SMIPCC only)

2. Transition to SMIPCC after pushback 1

3. Transition to SMIPCC after pushback 2

4. Transition to SMIPCC after pushback 3

5. SMIPCC not used (TS only).

The operating pushbacks (phases) and final pit limit were designed for both systems with a bench height of 15 m and a face slope angle of 65 degrees. Figures 7 to 10 show the plan view of four pushbacks using TS and SMIPCC.

 

 

 

 

 

 

 

 

The final operating pit limit of scenarios 1 to 4 is the same, with the amount of waste of these four scenarios increasing by approximately 90 Mt compared to the fifth scenario (pure TS), and 100 Mt compared to the optimal final pit shell. This increase is due to the additional waste generated during construction of new ramps for the conveyor path and switchbacks in the truck ramp to avoid intersecting the conveyor and truck roads. Details of the increasing waste in each designed phase of the two systems (compared to the optimal pit shell) are described in Table II. The total amount of waste in the final pit limit is increased by 7.4% under the SMIPCC scenario compared to TS. However, the amount of ore does not change.

 

 

Due to the characteristics of the mine, the need for trucks with high capacity is evident. Caterpillar 793C trucks (Caterpillar, 1998) with a capacity of 221 t were found to be suitable. According to the performance of this truck, the cycle time was calculated for each phase.

The centre of gravity of waste and ore was used to measure transportation time in the TS system along the path length. In the SMIPCC system, four centres of gravity were considered -two for ore blocks above and below the crusher, and two for waste blocks. Transportation time was calculated using the abovementioned centres of gravity and the specific paths for hauling ore and waste from each of them. Table III contains the information used for calculating the efficiency of the TS system.

 

 

Using this information, efficiency was calculated at 62% for each shovel and 70% for each truck. Data for calculating the required number of trucks is presented in Table IV.

 

 

As shown in Table II, the amount of stripping required increases from the first to the fourth pushback. As such, the number of machines for executing each phase needs to gradually increase. Since ore production capacity has been set at 20 Mt/a, the capacity of the conveyor for ore extraction will remain consistent.

Considering three 8-hour work shifts and 310 working days in a year (55 days for repair, replacement, daily and monthly servicing), the required capacity of the ore conveyer was estimated at 2690 t/h. The capacity of the stripping conveyor, however, will differ in each phase. Thus, the equipment required in each phase needs to be computed separately. A brief description of the machines required for each phase is provided in Table V. For example, if it is decided to mine using the third scenario, the machinery for the first two phases will be chosen from the TS system and for the remaining two phases from the SMIPCC system.

Based on economic analysis of the various scenarios, it is apparent that the purchase of single large waste conveyors and spreaders is preferred over multiple lower capacity sets of equipment. Therefore, the required machinery for each scenario has been selected based upon the lowest CDC. Capital and operating costs of the equipment of both systems are calculated using InfoMine cost tables and are presented in Table VI. Different components of the SMIPCC haulage system for each scenario are presented in Table VII. Economic studies for each scenario are presented in Table VIII. The most economical haulage option is chosen between the TS and SMIPCC alternatives.

The sensitivity of the optimal scenario and transition point to discount rate is shown in Figure 11. As indicated, the optimal transition point between TS and SMIPCC systems is not reasonably related to the discounted rate. The second scenario, with a depth of 335 m for transition from TS to SMIPCC, has the lowest CDC across all discount rates. A comparison between pure TS and pure SMIPCC shows that the pure SMIPCC system has a higher economic advantage (lower CDC) than the pure TS system at a zero discounted rate. This advantage continues up to the 10% discounted rate. At a discounted rate of 10% or more, the pure TS system has a lower CDC than pure SMIPCC because the operating costs do not affect the CDC significantly at a high discounted rate in the latter periods of mine life. Therefore, the pure TS system with a lower capital cost than the SMIPCC will be selected as the optimum system. Choosing between pure TS and pure SMIPCC systems is highly sensitive to the discount rate, but the optimum transition point is not.

 

Conclusion

The SMIPCC system is one of the most appropriate options for mining deeper and lower-grade deposits due to its lower operating costs, which can thus reduce the cut-off grade. However, a greater capital investment is required in comparison to conventional truck and shovel systems. Whether or not the greater initial capital investment can be recouped throughout the mine life from lower operating costs should be the subject of technical and feasibility studies in order to identify the most appropriate system(s) and the point at which a transition may occur.

For the case study that was presented, a depth of 335 m was determined as the optimum transition point from TS to SMIPCC based on a CDC analysis. It was also found that the transition point is not sensitive to the discount rate. However, because the operating costs do not influence the CDC substantially in the latter periods of mine life, with a high discount rate the pure TS system, with a lower capital cost, is the optimum when deciding between pure TS and pure SMIPCC systems. Conversely, at a lower discounted rate pure SMIPCC is more economically viable than the TS system.

 

Future work

Future research should investigate the uncertainty related to equipment operating and capital costs. This should perhaps be combined with determining the optimum ultimate pit limit and mine plan based on mathematical modelling. Further work addressing the optimal transition point between a TS system and a SMIPCC system relating to the optimum location and relocation of the semi-mobile crusher should also be considered. Even though fully mobile in-pit crusher conveyor (FMIPCC) systems require more extensive redesign of the mining operation due to the introduction of sequencing constraints, there are further economic benefits that could result from such a system which could also be addressed.

 

Acknowledgment

The authors would like to acknowledge the valuable comments and suggestions of the editor and anonymous reviewers, which have improved the quality of this paper. Thanks are also extended to Dr. Mehdi Rahmanpour for his initial comments in completing the paper.

 

References

Abbaspour, A., Drebenstedt, C., Paricheh, M., and Ritter, R. 2019. Optimum location and relocation plan of semi-mobile in-pit crushing and conveying systems in open-pit mines by transportation problem. International Journal of Mining, Reclamation and Environment, vol. 33, no. 5. pp. 297-317. https://doi.org/10.1080/17480930.2018.1435968        [ Links ]

Caterpillar. 1998. Caterpillar Performance Handbook. Edition 29, Section of Construction & Mining Trucks Construction & Mining Tratrors. pp. 36-43.         [ Links ]

Dean, M., Knights, P., Kizil, M., and Nehring, M. 2015. Selection and planning of fully mobile in-pit crusher and conveyor systems for deep open pit metalliferous applications. Proceedings of the Third International Future Mining Conference, University of New South Wales, Australia. Australasian Institute of Mining and Metallurgy, Melbourne. pp. 219-225.         [ Links ]

Dos Santos, J. 1984. Sandwich belt high angle conveyors-applications in open pit mining. Bulk Solids Handling, vol. 4, no. 1. pp. 67-77.         [ Links ]

Dos Santos, I.A. 2016. Sandwich belt high angle conveyors coal mine to prep plant and beyond. Proceedings of the XVIII International Coal Preparation Congress, Saint-Petersburg, Russia. Springer. pp. 111-117.         [ Links ]

Dos Santos, J.A. and Stanisic, Z. 1986. In-pit crushing and high angle conveying in a Yugoslavian copper mine. International Journal of Surface Mining, Reclamation and Environment, vol. 1, no. 2. pp. 97-104. https://doi.org/10.1080/09208118708944108        [ Links ]

Frizzell, E.M. and Martin, T.W.1992. In-pit crushing and conveying. Mining Engineering Handbook. Hartman, H.L. (ed.). Society for Mining, Metallurgy, and Exploration, Littleton, CO. pp. 1343-1351.         [ Links ]

Hay, E., Nehring, M., Knights, P., and Kizil, M.S. 2020. Ultimate pit limit determination for semi mobile in-pit crushing and conveying system: a case study. International Journal of Mining, Reclamation and Environment, vol. 34, no. 7. pp. 498-518. https://doi.org/10.1080/17480930.2019.1639006        [ Links ]

Hays, R.M. 1983. Mine planning considerations for in-pit crushing and conveying systems. Proceedings of the SME-AIME Fall Meeting. Brent Hiskey, J. (ed.) American Institute of Mining, Metallurgical and Petroleum Engineers, New York. pp. 3--41.         [ Links ]

Huss, C., Reisler, N., and Almond, R. 1983. Practical and economic aspects of in-pit crushing conveyor systems. Proceedings of the SME-AIME Fall Meeting. Brent Hiskey, J. (ed.). American Institute of Mining, Metallurgical and Petroleum Engineers, New York. pp. 15-31.         [ Links ]

Kesimal, A. 1997. Different types of belt conveyors and their applications in surface mines. Mineral Resources Engineering, vol. 6, no. 4. pp. 195-219.         [ Links ]

Kochanowsky, B. 1961. Portable crusher for open pit and quarry operations. Transactions of the American Institute of Mining, Metallurgical Petroleum Engineers, vol. 220. pp. 271-274.         [ Links ]

Koehler, F. 2003. In-pit crushing system the future mining option. Proceedings of the Twelfth International Symposium on Mine Planning and Equipment Selection. Australasian Institute of Mining and Metallurgy, Melbourne. pp. 371-376.         [ Links ]

Konak, G., Onur, A.A., and Karakus, D. 2007. Selection of the optimum in-pit crusher location for an aggregate producer. Journal of the Southern African Institute of Mining and Metallurgy, vol. 107, no. 3. pp.161-166.         [ Links ]

Liu, D. and Pourrahimian, Y. 2021. A framework for open-pit mine production scheduling under semi-mobile in-pit crushing and conveying systems with the high-angle conveyor. Mining, vol. 1, no. 1. pp. 59-79. https://doi.org/10.3390/mining1010005        [ Links ]

Mitchell, J. and Albertson, D. 1985. High angle conveyor offers mine haulage savings. Proceedings of the International Materials Handling Conference, BeltCon 3, Johannesburg. South Africa. South African Institute of Materials Handling. Vol. 3. pp. 9-11.         [ Links ]

Nehring, M., Knights, P.F., Kizil, M.S., and Hay, E. 2018. A comparison of strategic mine planning approaches for in-pit crushing and conveying, and truck/shovel systems. International Journal of Mining Science and Technology, vol. 28, no. 2. pp. 205-214. https://doi.org/10.1016/j.ijmst.2017.12.026        [ Links ]

Norgate, T. and Haque, N. 2013. The greenhouse gas impact of IPCC and ore-sorting technologies. Minerals Engineering, vol. 42. pp. 13-21. https://doi.org/10.1016/j.mineng.2012.11.012        [ Links ]

Nunes, R.A., Delboni, H., Tomi, G.D., Infante, C.B., and Allan, B. 2019. A decision-making method to assess the benefits of a semi-mobile in-pit crushing and conveying alternative during the early stages of a mining project. REM-International Engineering Journal, vol. 72. pp. 285-291. https://doi.org/10.1590/0370-44672018720109        [ Links ]

Osanloo, M. 2012. Future challenges in mining division, are we ready for these challenges? Do we have solid educational program?. Proceedings of the 23rd Annual General Meeting of the Society of Mining Professors, Poland. Wroclaw University of Technology. pp. 29-39.         [ Links ]

Paricheh, M. and Osanloo, M. 2019a. Concurrent open-pit mine production and in-pit crushing-conveying system planning. Engineering Optimization, vol. 52, no. 10. pp. 1780-1795. https://doi.org/10.1080/0305215X.2019.1678150        [ Links ]

Paricheh, M. and Osanloo, M. 2019b. How to exit conveyor from an open-pit mine: A theoretical approach. Proceedings of the 27th International Symposium on Mine Planning and Equipment Selection - MPES 2018, Perth, Australia. Springer. pp. 319-334.         [ Links ]

Paricheh, M. and Osanloo, M. 2019c. A new search algorithm for finding candidate crusher locations inside open pit mines. Proceedings of the International Symposium on Mine Planning & Equipment Selection - MPES 2018, Perth, Australia. Springer. pp. 10-25.         [ Links ]

Paricheh, M., Osanloo, M., and Rahmanpour, M. 2017. In-pit crusher location as a dynamic location problem. Journal of the Southern African Institute of Mining and Metallurgy, vol. 117, no. 6. pp. 599-607.         [ Links ]

Paricheh, M., Osanloo, M., and Rahmanpour, M. 2018. A heuristic approach for in-pit crusher and conveyor system's time and location problem in large open-pit mining. International Journal of Mining Reclamation and Environment, vol. 32, no. 1. pp. 35-55. https://doi.org/10.1080/17480930.2016.1247206        [ Links ]

Purhamadani, E., Bagherpour, R., and Tudeshki, H. 2021. Energy consumption in open-pit mining operations relying on reduced energy consumption for haulage using in-pit crusher systems. Journal of Cleaner Production, vol. 291. p. 125228. https://doi.org/10.1016/j.jclepro.2020.125228        [ Links ]

Rahmanpour, M., Osanloo, M., Adibee, N., and AkbarpourShirazi, M. 2014. An approach to locate an in pit crusher in open pit mines. International Journal of Engineering-Transactions C: Aspects, vol. 27, no. 9. pp. 1475-1484.         [ Links ]

Roumpos, C., Partsinevelos, P., Agioutantis, Z., Makantasis, K., and Vlachou, A. 2014. The optimal location of the distribution point of the belt conveyor system in continuous surface mining operations. Simulation Modelling Practice and Theory, vol. 47. pp. 19-27.         [ Links ]

Samavati, M., Essam, D.I., Nehring, M., and Sarker, R. 2018. Open-pit mine production planning and scheduling: A research agenda. Data and Decision Sciences in Action. Sarker, R., Abbass , H.A., Dunstall, S., Kilby, P., Davis,R., and Young, L. (eds). Springer. pp. 221-226.         [ Links ]

Szalanski, S. 2010. Reducing IPCC removal costs - is IPCC the answer? Proceedings of the International Future Mining Conference, Sydney, NSW, 4-6 November 2015.Australasian Institute of Mining and Metallurgy, Melbourne.         [ Links ]

Terezopoulos, N.G. 1988. Continuous haulage and in-pit crushing in surface mining. Mining Science and Technology, vol. 7, no. 3. pp. 253-263.         [ Links ]

Tudeshki, A., Hardebusch, T., Rebehn, T., and RoBbach, S. 2004. cost reduction by optimization of the primary crusher position. Bulk Solids Handling, vol. 24, no. 1. pp. 20-24.         [ Links ]

Tutton, D. and Streck, W. 2009. The application of mobile in-pit crushing and conveying in large, hard rock open pit mines. Proceedings of the Mining Magazine Congress, Niagara-on-the-Lake, Canada. Mining Magazine, London, UK.         [ Links ]

Utley, R.W. 2011. In-pit crushing. SME Mining Engineering Handbook, 3rd edn. Society for Mining, Metallurgy and Exploration Inc, Englewood, CO. pp. 941-956.         [ Links ]

Zimmermann, E. and Kruse, W. 2006. Mobile crushing and conveying in quarries - A chance for better and cheaper production! Proceedings of the 8th International Symposium Continuous on Surface Mining, Mainz, Aachen. RWTH Aachen University. Vol. 1. pp. 481-487. https://www.911metallurgist.com/blog/wp-content/uploads/2015/12/mobile-crushing.pdf        [ Links ]

 

 

Correspondence:
M. Nehring
M. Shamsi
Email: m.nehring@uq.edu.au; shamsi.miner@gmail.com

Received: 9 Mar. 2021
Revised: 14 Aug. 2021
Accepted: 24 Aug. 2021
Published: September 2021

Creative Commons License All the contents of this journal, except where otherwise noted, is licensed under a Creative Commons Attribution License