SciELO - Scientific Electronic Library Online

 
vol.19 número1 índice de autoresíndice de materiabúsqueda de artículos
Home Pagelista alfabética de revistas  

Servicios Personalizados

Articulo

Indicadores

Links relacionados

  • En proceso de indezaciónCitado por Google
  • En proceso de indezaciónSimilares en Google

Compartir


South African Journal of Industrial Engineering

versión On-line ISSN 2224-7890
versión impresa ISSN 1012-277X

S. Afr. J. Ind. Eng. vol.19 no.1 Pretoria  2008

 

Computerised information systems: Comparison of relative impacts on planned project duration within a multi-project environment

 

 

S. Govender; H. Steyn

Department of Engineering and Technology Management, University of Pretoria, South Africa herman.steyn@up.ac.za

 

 


ABSTRACT

As more organisations acquire project management computerised information systems (CIS) to ensure the efficient scheduling of projects, there is increasing interest in the extent to which various CIS contribute to a reduction in planned project duration. However, there seems to be no empirical research that suggests that CIS have a positive impact on planned duration or how relative impacts could vary when different CIS are implemented. This paper reports on experimental research that evaluates and draws comparisons between the relative impacts of three CIS on planned project delivery within a specific, real, multi-project environment, and investigates the reasons for such variations.


OPSOMMING

Namate meer organisasies gerekenariseerde inligtingstelsels bekom om doelmatige skedulering van projekte te verseker, neem belangstelling toe oor die mate waartoe verskillende stelsels bydra tot die verkorting van die beplande tydsduur van projekte. Dit blyk egter dat geen empiriese inligting bestaan wat aandui dat hierdie rekenaarstelsels 'n positiewe impak op beplande duur van projekte het of hoe die impak varieer met die gebruik van verskillende stelsels nie. Hierdie artikel rapporteer oor empiriese navorsing wat die relatiewe impak van drie rekenaarstelsels op beplande projek aflewering in 'n spesifieke, werklike multi-projek omgewing evalueer. Die redes vir die verskille wat gerapporteer word, word ook ondersoek.


 

 

“Full text available only in PDF format”

 

 

REFERENCES

[1] Al-jibouri, S. 2002. Effects of resource management regimes on project schedule. International Journal of Project Management, 20(4), 271-277.         [ Links ]

[2] Chelaka, M., Abeyasinghe, L., Greenwood, D. J. & Johansen, D. E. 2001. An efficient method for scheduling construction projects with resource constraints. International Journal of Project Management, 19(1), 29-45.         [ Links ]

[3] Cohen, I., Madelbaum, A. & Shtub, A. 2004. Multi-project scheduling and control: A process-based comparative study of the critical chain methodology and some alternatives. Project Management Journal, 35(2), 39-50.         [ Links ]

[4] Cooper, R.G., Edgett, S.J. & Kleinschmidt, E.J. 2001. Portfolio management. Fundamental to new product success. Working Paper No. 12. Product Development Institute.         [ Links ]

[5] Dass, S. & Steyn, H. 2005. An exploratory assessment of project duration in multiple-project schedules where resources are allocated by the theory of constraints method. Pretoria: University of Pretoria: Department of Engineering and Technology Management.         [ Links ]

[6] Fox, T. & Spence, J. 1998. Tools of the trade: A survey of project management tools. Project Management Journal, 29(3), 20-27.         [ Links ]

[7] Jugdev, K. & Thomas, A. 2002. Project management maturity models: The silver bullets of competitive advantage? Project Management Journal, 33(4).         [ Links ]

[8] Levine, H. 2005. Benefits from expediting projects: Expedite your way to lower costs and higher profits. Available from: http://www.sciforma.com.         [ Links ] [Accessed 02 June 2006]

[9] Meredith, J. R. & Mantel, S. J. 2006. Project management - a managerial approach, 6th edition, John Wiley & Sons, Inc. New York.         [ Links ]

[10] Regnier, E. 2005. Activity completion times in PERT and scheduling network simulation, Part II. Monterey, California: DRMI Newsletter, Defence Resources Management Institute, Naval Postgraduate School.         [ Links ]

[11] Steyn, H. 2003. Comparison between and combinations of different approaches to accelerate engineering projects. SA Journal of Industrial Engineering, 14(2).         [ Links ]

[12] Tsai, D.M. & Chiu, H.N. 1996. Two heuristics for scheduling multiple projects with resource constraints. Construction Management and Economics, 14(4), 325-340.         [ Links ]

[13] Viljoen, P.J. & Steyn, H. 2005. A model for increasing productivity of project portfolio delivery systems. Pretoria: University of Pretoria: Department of Engineering and Technology Management.         [ Links ]

 

 

1 The author was enrolled for the MPM programme at the Department of Engineering and Technology Management, University of Pretoria

Creative Commons License Todo el contenido de esta revista, excepto dónde está identificado, está bajo una Licencia Creative Commons