SOTO, I.; ANANI, A.  y  CORDOVA, E.. A discrete event simulation approach for mine development planning at Codelco's New Mine Level. J. S. Afr. Inst. Min. Metall. [online]. 2022, vol.122, n.10, pp.549-560. ISSN 2411-9717.  http://dx.doi.org/10.17159/2411-9717/2045/2022.

The new caving megaprojects that are planned to go into production in the next decade have scheduled horizontal developments at very high rates, which are difficult to achieve. Research has been conducted that seeks to model the construction times for underground developments to determine the feasibility of achieving the planned rates. However, these previous attempts do not consider all the operational aspects that make up the mine development cycle. Here, we present a discrete event simulation (DES) model that individualizes each unit operation of the development cycle to determine the construction rates that new projects will be able to attain. The developed model was applied to the New Mine Level (NML) of the El Teniente Division (DET). The results indicate that it would be impractical to achieve the advance rates scheduled in the original plans if the unit operations of the mine continue to be executed using the status quo. The metres developed after six years in the sections analysed can be significantly improved by changing the maintenance strategy for the equipment (457 metres increase), orepass availability (194 metres increase), and the initial planning sequence (1 598 metres increase). It is recommended that the mine implements a flexible maintenance strategy, defines a strategy to ensure and increase orepass availability to contractors, and makes use of current simulation tools for a more robust development sequence planning.

Palabras clave : mine development; mine planning; caving; OR in natural resources; discrete event simulation.