Services on Demand
Article
Indicators
Related links
- Cited by Google
- Similars in Google
Share
Journal of the Southern African Institute of Mining and Metallurgy
On-line version ISSN 2411-9717
Print version ISSN 2225-6253
Abstract
ANGELOV, A.A. and NAIDOO, K.. Plan compliance process for underground coal mines. J. S. Afr. Inst. Min. Metall. [online]. 2010, vol.110, n.5, pp.241-250. ISSN 2411-9717.
SYNOPSIS This paper presents a unique method of monitoring the effectiveness of the planning process as well as the execution of mine plans. The method primarily determines the degree of deviation from the original mine plans by comparing actual mined areas to initially planned mining areas. The performance of mining operations is also measured by comparing actual and planned tonnages for a particular period. Once the degree of deviation from mine plans has been established the cause/s of the deviation can be determined through a simple fault tree analysis. Accurate identification of the reasons of deviation can aid the mine in selecting possible methods to correct the deviation. It is, however, beyond the scope of this paper to discuss the methods employed in correcting such deviations, as each mining operation will have unique causes of plan deviation and methods of remedying them. Deviations from the plan greatly affect the yields obtainable, which in turn affects the life of mine, thus having negative economic and financial implications. Accordingly, this paper presents a project management method which aims to reduce risk by improving planning systems to ensure optimum overall extraction of coal reserves.