KAGOGO, T.S.  and  STEYN, H.. Effect of scope readiness on capital projects in mining: a Namibian case study. S. Afr. J. Ind. Eng. [online]. 2019, vol.30, n.1, pp.257-269. ISSN 2224-7890.  http://dx.doi.org/10.7166/30-1-2086.

Alhoewel die bestek-beskrywing van 'n projek algemeen beskou word as 'n sleutelelement in die suksesvolle bestuur van 'n projek, is baie min navorsing hieroor gedoen. Hierdie artikel ondersoek die verwantskap tussen die gereedheid van bestek-beskrywings en die sukses van projekte in die Namibiese mynbou-industrie. 'n Opname is gedoen op tien projekte in sewe Namibiese mynbou maatskappye. Die Projek Definisie Gereedheid Indeks (PDRI) instrument is gebruik as aanwyser van die gereedheid van die bestekdefinisie, terwyl kosteprestasie en skedule-prestasie as aanduiding van projeksukses gebruik is. Ondersteuning is gevind vir die stelling dat die gereedheid van 'n projek se bestekomskrywing skedule-prestasie bevorder, maar die verwantskap tussen PDRI telling en kosteprestasie was minder oortuigend.

        · abstract in English     · text in English     · English ( pdf )

 